Total Pageviews

Friday 24 August 2012

The crane arrives


Some of the oak frames proved too large or too difficult to put in place for the Merlo telehandler so on Monday Gary Hill from Vic Haines Transport arrived with his crane to help out. First the large front dormer was lifted quickly into place within minutes – completing installation of the three dormer windows. 

 The prime task this morning was to position the large south facing oak window in place in the main bedroom. Will carefully collected the frame from the barn and Gary prepared the two slings which would carry the frame right over the roof of the house. 



The combination of experience and expertise coupled with a great sense of humour soon swung the huge window into position just cms from its final resting place where it was manually located and strapped in place.




An even larger oak frame weighing well over a tonne has yet to be installed as well as the equally heavy frames for the conservatory, but these will have to wait until we have finished with the scaffolding.

No comments:

Post a Comment