There
are certainly other low energy houses in the UK with passive slabs but they are
usually built by specialist companies with materials and often manpower from
Germany, Sweden and Ireland. The
Colemans Hill slab was built by two non-specialists – with a little help from
friends at the week-end. It’s not rocket
science but it is time consuming, especially for a house with 22 corners, and involves
some creative and innovative thinking.
“The
Passive Slab is an Insulated Foundation System that is PassiveHaus
approved to deliver the lowest U-value available on the market (as low as 0.08W/m.K)
and eliminates the critical wall to floor cold bridge. Expanded Polystyrene is
used to wrap the foundation of the building ensuring there is no thermal break
between the wall and the foundation. The structural strength of the Passive
Slab results from the combination of Expanded Polystyrene (EPS 300), concrete
and steel“.
Perimeter walls built up to DPC level |
Coarse sand is added over the compacted stone |
Sand is built up to about 30mm to allow for compaction |
and then compacted using a whacker plate . . .
. . . before levelling ready for the polystyrene
ESP300 L sections are first laid around the perimeter
Corner showing half lap joint
A further 250mm of EPS300 is added to the
base section and 500mm pieces of EPS300 placed on top
1200X1200 mm EPS100 are added to fill layer 1
followed by more EPS100 to complete layer 2
A DPC membrane was then laid over layer 2.
No radon barrier was required in this location.
Steel mesh was then laid on layer 3 . . .
. . . and a strip supported on clay "chairs" added
around the perimeter to form a ring beam
around the perimeter to form a ring beam
Areas supporting load bearing walls have no layer 3
and additional steel mesh is added . . .
and additional steel mesh is added . . .
. . . these areas and the ring beam will therefore contain 200mm of concrete whereas the main slab is only 100mm thick |
Whilst EPS can be cut with a saw it produces a lot of polystyrene granules so we built a simple hot wire cutter which although a little slower, produced a cleaner cut and no mess.
After wiring and spacing all the steelwork the slab was finally ready for the concrete pour. Regrettably it did not prove possible to use the ultra low carbon cement as CEMEN was still working on the new production facility and the bagging plant was not operational.
Concrete filling the 400mm perimeter "ring beam" |
No comments:
Post a Comment